Introduction & Background

The Global Platform for Sustainable Natural Rubber (GPSNR) is an international, multi-stakeholder, voluntary membership initiative seeking to lead improvements in the socioeconomic and environmental performance of the natural rubber value chain. Members of the platform include tire manufacturers, rubber suppliers and processors, vehicle makers and NGOs. 

 

The Manufacturer’s Subgroup (SG) consists of GPSNR members who are rubber product manufacturers only.  The SG is seeking a consultant/field to map their supply shed (i.e., all the farms that they are sourcing from) focusing on polygon mapping techniques in complex supply chains such as in Indonesia, Malaysia and Thailand – each with a separate RFP, and report on the price and time required for each polygon mapped.

Objectives

The goal of the project is to investigate what effort (i.e., time and cost) may be required for a rubber processor to map their supply chain in complex supply chains in Indonesia. 

The consultant is to map small holder farmers in selected regions within Indonesia. Manufacturers will specify the regions to be mapped at a later date. 

The service provider should work with the Manufacturer’s Subgroup and the participating processors from Indonesia and their dealers to:

 

  1. Keep track of the time and costs of all mapping related activities throughout the study, calculate time and cost of mapping each polygon, and provide them to their GPSNR Point of Contact at the end of the survey.

  2. Register farmers using a provided data logger application. The service provider is welcomed to use their own data logger application. 

 

Scope of Work/Expected Deliverables

Specifically, GPSNR expects the consultant to:

  1. Map regions of rubber producers supplying to the participating processor in Indonesia via polygon mapping. 

    1. Single GPS coordinates should not be utilised irrespective of the size of the plantation. 

    2. Geo mapping to include coordinates up to 6 decimal places in geoJSON format 

    1. Store/transfer geo location polygons mapped, to a 3rd party database as designated. 

    2. Bi-weekly progress reports 

    3. Ensure compliance to applicable local and global data privacy norms and regulations such as but not limited to GDPR, PDPA, etc.

  1. We would like a detailed account of the resources: 

    1. Price per polygon mapped – Cost per unit (per Farmer/Plot/Polygon) 

    2. Timeline to map Polygons per day (eg 18 months to map X polygons)

  1. A recommendation of the scalability of this pilot

    1. Can the same estimated cost/time/labour be replicated in other regions/jurisdictions within the same country?

    2. E.g., $X/farm is calculated but is not scalable due to what reason(s).

  2. Interested parties should submit the quote for the following – 

    1. For mapping polygons (cost per Ha)

    2. For mapping polygons + completing set of questionnaires as a part of risk assessment

  3. Comply with applicable data privacy norms and regulations (including but not limited to GDPR and PDPA).

  4. An optional activity that service providers could provide is the ability to integrate a transactional traceability function (own or 3rd party as designated)

Proposal Format and Contents

The proposal should include the following:

 

  1. A workplan that outlines the key activities towards the deliverables outlined in Expected Deliverables above

  2. The timeline and key stages of operations based on Project Timeline below 

  3. Budget, including detailed breakdown of expected manpower, logistics, and costs as mentioned above

  4. Description of past work and technical expertise that is relevant to this RFP

A list of project team members with their roles in the project and associated qualifications.

Submission Guidelines & Requirements 

The following submission guidelines & requirements apply to this Request for Proposal: 

 

  1. Proposals will only be accepted from individuals or firms with experience relevant to this project. 

  2. Examples of previous relevant work should be provided. 

  3. A technical proposal must be provided that is not more than 4 pages. This technical proposal must provide an overview of the proposed solution as well as resumes of all key personnel performing the work. In addition, the technical proposal should provide a proposed schedule and milestones, as applicable. 

  4. A price proposal must be provided that is not more than 1 pages. This price proposal should indicate the overall fixed price for the project as well as hourly rates and an estimated total number of days. 

  5. Proposals must be signed by a representative that is authorized to commit bidder’s company. 

  6. Proposals must be received prior to the 25th of September to be considered. Proposals should be submitted to stefano.savi@gpsnr.org and aidan@gpsnr.org for consideration. 

  7. GPSNR reserves the right to amend the scope and budget of this RFP in order to get the most suitable consultant for each topic. 

Project Timelines

 

RFP Published

4 Sep 2023

Proposal Submission Deadline

25 Sep 2023

Contract Awarded

9 Oct 2023

Initial methodology presentation and Q&A with subgroup

23 Oct 2023

Bi-weekly progress updates

23 Oct till project conclusion

Other milestones to be agreed upon during initial Q&A

 

 

Budget

The Platform is anticipating that a total budget of no more than 20USD/ha be allocated to this engagement and more competitive quotations will be favoured. 

 

Payment terms shall be:

  • 20% at the signing of the contract

  • 30% at the midpoint date to be agreed upon and memorialized in the contract based on the submitted work plan

  • 50% to be agreed based on mutually agreed milestones

The allocation of the payment shall be based on the net amount after travel expenses, if deemed necessary by both the consultant and Secretariat, are incurred and documented.

Evaluation Factors

GPSNR will rate proposals based on the following factors, with cost being the most important factor:

  1. Responsiveness to the requirements set forth in this Request for Proposal

  2. Relevant past performance/ experience

  3. Samples of work

  4. Cost, including an assessment of total cost of ownership

  5. Technical expertise/experience of bidder and bidder’s staff

 

GPSNR reserves the right to award to the bidder that presents the best value to GPSNR as determined solely by GPSNR in its absolute discretion.

More To Explore

(CLOSED) Request for Proposal GPSNR POLICY IMPLEMENTATION GUIDANCE AND REPORTING REQUIREMENTS

Introduction & Background

The Global Platform for Sustainable
Natural Rubber (GPSNR), is an international, multi-Stakeholder, voluntary
membership initiative seeking to lead improvements in the socioeconomic and
environmental performance of the natural rubber value chain. Development of the
GPSNR was initiated by the CEOs of the World Business Council for Sustainable
Development (WBCSD) Tire Industry Project (TIP) in 2018. Members of the
platform include tire manufacturers, rubber suppliers and processors, vehicle
makers, smallholder rubber growers, and NGOs. Representatives from each of
these stakeholder groups have contributed to the development of the
Singapore-based platform and the wide-reaching set of priorities that will
define GPSNR strategies and objectives.

Through a process led by the Policy
Toolbox and Implementation Guidance Working Group (WG1), the General Assembly
approved a Policy Framework in September 2020 that outlines the specific
commitments to sustainable natural rubber that GPSNR company members must
include in their public policies or other relevant documents.  GPSNR ordinary member companies are required
to create new or update existing policies to align with the Policy Framework by
March 2021 (companies will have a possibility to request an extension provided
they can demonstrate progress in developing or updating their policies).

WG1 is finalizing Baseline
Reporting Requirements (BRRs) for ordinary member companies to assess where
they are in their sustainability journey. 
Once WG1 finalizes the BRRs, it will send them to the GPSNR Executive
Committee (EC) for review and approval. 
Company members will be expected to provide the GPSNR Secretariat with
their baseline reporting data in 2021 (date to be confirmed).

The next step is for GPSNR to
develop the Implementation Guidance and future Reporting Requirements
as they pertain to the specific commitments laid out in the GPSNR policy
components.  The Implementation Guidance
and Reporting Requirements will vary depending on where a member company sits
within the natural rubber supply chain, so this work will be organized by the
following stakeholder categories: 
natural rubber producers/processors and traders, tire makers and other
natural rubber product manufacturers, and auto makers and other end users. 

In order to achieve this, the
Platform is seeking a fixed term consultancy to facilitate the development of
the Implementation Guidance and Reporting Requirements for each of the 3
stakeholder categories.  While WG1 will
provide oversight to this process, GPSNR will invite the creation of focus
groups for each of the three stakeholder categories to enable broader participation
of members from each of the stakeholder groups (although focus groups can also
include members from other stakeholder categories).  The consultant first will facilitate the
development of the Implementation Guidance for each of the 3 categories by
reviewing guidance and requirements from other initiatives, such as the
Accountability Framework, as well as certification schemes such as RSPO, FSC,
PEFC, Cocoa Forests Initiative, and others to prepare draft guidance.  The consultant will gather input from the WG1
Co-chairs and the GPSNR Secretariat on the draft, and will then facilitate
various rounds of discussion with the focus groups to finalize the guidance for
each stakeholder category.   All comments
will be recorded in a spreadsheet and the decision-making process for
incorporating or rejecting comments will be clearly documented.  The Implementation Guidance will include a
corresponding Action Plan template for companies to submit to GPSNR on an
annual basis to indicate which activities they intend to focus on in the coming
year.

Once the focus groups have agreed on the language for the Implementation Guidance and the Action Plan template, they will be submitted to the broader WG for approval.   Meanwhile, the Consultant will develop the Reporting Requirements for each stakeholder category.  The Reporting Requirements will build off of the BRRs and will align with the Implementation Guidance.  The consultant will also review other reporting schemes that members report into, such as ZSL Spott, Global Reporting Initiatives, CDP Forests, and Ecovadis to identify where GPSNR requirements are similar and to align wherever possible.  The Consultant will work with the appropriate focus groups to further design the Reporting Requirements for each stakeholder category.  Once approved by the focus groups, the Reporting Requirements will go to the broader WG1 for approval, and then on to the EC.

Submission Guidelines & Requirements

The following submission guidelines & requirements apply to this Request for Proposal:

  1. Proposals will only be accepted from individuals or firms with experience relevant to this project.
  2. Examples of previous relevant work should be provided as well.
  3. A technical proposal must be provided that is not more than 6 pages. This technical proposal must provide an overview of the proposed solution as well as resumes of all key personnel performing the work. In addition, the technical proposal should provide a proposed schedule and milestones, as applicable.
  4. A price proposal must be provided that is not more than 1 page. This price proposal should indicate the overall fixed price for the project as well as daily rates and an estimated total number of days.
  5. Proposals must be signed by a representative that is authorized to commit bidder’s company.
  6. Proposals must be received prior to 5th February 2021 to be considered. Proposals should be submitted to aidan@gpsnr.org and stefano.savi@gpsnr.org for consideration.
  7. GPSNR anticipates shortlisting at least two individuals or firms with which to have more in-depth discussions, and will make an award to one of these short-listed individuals or firms.
  8. GPSNR reserves the right to amend the scope of this RFP in order to get the most suitable consultant.

RFP & Project Timelines

The Request for Proposal timeline is as follows:

Proposal
submitted by consultant to stefano.savi@gpsnr.org

 
05/02/2021
Selection of Top Bidders /
Notification to Unsuccessful Bidders
 
12/02/2021
Contract Award /
Notification to Unsuccessful Bidders
 
19/02/2021
Work to commence no later than 22/02/2021
Need-date for project completion 22/06/2021

Budget

The Platform is anticipating that a total budget of no more than 35,000 SGD be allocated to this engagement.

Payment terms shall be:
● 20% at the signing of the contract
● 30% at the midpoint date to be agreed upon and memorialized in the contract based on the submitted work plan
● 50% on delivery of the final report

Evaluation Factors

GPSNR will rate proposals based on the following factors:

  1. Responsiveness to the requirements set forth in this Request for Proposals
  2. Relevant past performance/experience
  3. Samples of work
  4. Cost, including an assessment of total cost of ownership.
  5. Technical expertise/experience of bidder and the bidder’s staff

GPSNR reserves the right to award to the bidder that presents the best value to GPSNR as determined solely by GPSNR in its absolute discretion.

View and download full RFP here

Proposals should be submitted to stefano.savi@gpsnr.org and aidan@gpsnr.org for consideration

(CLOSED) Request for Proposal – Webpage design consultancy

Webpage design consultancy

Background

At GPSNR, we bring together companies, smallholders, academia and civil society to transform the natural rubber supply chain into a sustainable, equitable and fair one.

Even though it was launched just in 2018, 50% of the world’s natural rubber demand already finds membership in GPSNR. This is only a small reflection of the amount of work that has taken place over the last three years.

Scope

To document important decisions and milestones and ensure institutional memory is well-recorded, GPSNR is seeking a User Interface/User experience consultant to design three web pages that record a timeline, GPSNR’s assurance roadmap and the structure and overview of its working groups.

Core tasks

Working closely with the GPSNR secretariat, the consultant will:

  • Create and finalize three web-page mockups (wireframes, prototypes, and corresponding user interface components like templates, stylesheets, scripts, images, etc).
  • Include four rounds of feedback for each mockup from the GPSNR secretariat and key stakeholders
  • Integrate components in the CMS to allow review and testing, and make corresponding adjustments based on feedback received.
  • Liaise with GPSNR’s CRM expert to ensure that the mockups are feasible for the GPSNR website
  • Work closely with GPSNR’s Communications Manager on translating content into user oriented design

Terms

  • The engagement will take place for a period of six weeks from 15 October to 26nd November 2021. Interim dates for wireframes and approvals will be mutually agreed upon after confirmation.

Necessary Competencies:

  • Solid understanding of the concepts of user experience, user interface design principles and conceptual design.
  • Expert knowledge in WordPress CMS and Elementor
  • Knowledge of Bootstrap, jQuery and AngularJS, HTML, and Elementor Shortcodes
  • Knowledge of industry-standard design tools such as Adobe Photoshop, Illustrator and Dreamweaver.
  • Knowledge of WordPress Content Management System, particularly with respect to page template design, will be considered an asset.
  • Eye for design and attention to detail are essential.

Submission Guidelines:

The following submission guidelines & requirements apply to this Request for Proposal:

  • Proposals will only be accepted from individuals or firms with experience relevant to this project.
  • Submissions must include
    1) a portfolio of previous work
    2) a paragraph describing how the consultant would approach such a project
    3) a financial proposal with a breakdown of how much each competent of the work would cost.
  • Proposals must be signed by a representative that is authorized to commit to the bidder’s company.
  • Proposals must be received by 4 October 2021 to be considered. Proposals should be submitted to bani.bains@gpsnr.org and stefano.savi@gpsnr.org for consideration.
  • To receive a copy of the draft content, applicants can email bani.bains@gpsnr.org

RFP and Project Timelines

Submission of Proposal 4/10/2021
Selection of top bidders and further conversations 7/10/2021
Contract award/notification to unsuccessful bidders 11/10/2021
Work commences no later than 15/10/2021

Budget

The Platform is anticipating that a total budget of no more than 6,000 Singapore Dollars (SGD) be allocated to this engagement.

Payment terms shall be:

20% at the signing of the contract

30% at the midpoint date to be agreed upon and memorialized in the contract based on the submitted work plan

50% on delivery of the final report

Evaluation Factors

GPSNR will rate proposals based on the following factors:

  • Responsiveness to the requirements set forth in this Request for Proposals
  • Relevant past performance / experience and / or any samples of past work
  • Cost, including an assessment of total cost of ownership.
  • Technical expertise/experience of bidder and the bidder’s staff

GPSNR reserves the right to award to the bidder that presents the best value to GPSNR as determined solely by GPSNR in its absolute discretion.